Bronx General Site Work (XG-114M)

  • Design
    100% complete 
  • Procurement
    100% complete 
  • Construction
    95% complete 

This multisite contract will reconstruct play equipment, safety surfacing, pavements and general site work at various locations in the Bronx.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: November 2013
Projected Completion Date:March 2014
Completion Date: June 2014

Procurement

Start Date: June 2014
Projected Completion Date:March 2015
Completion Date: July 2015

Construction

Start Date: July 2015
Projected Completion Date:January 2017
Adjusted Completion Date: March 2017

Understand how we build parks.

Funding

Total Funding: $2,378,000
Funding Sources:
  • Mayor
  • City Council

Locations

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 02/24/2017