Bronx General Site Work (XG-114M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will reconstruct play equipment, safety surfacing, pavements and general site work at various locations in the Bronx.

Project Timeline

Design

Start Date: November 2013
Projected Completion Date: March 2014
Completion Date: June 2014

Procurement

Start Date: June 2014
Projected Completion Date: March 2015
Completion Date: July 2015

Construction

Start Date: July 2015
Projected Completion Date: January 2017
Completion Date: March 2017

Understand how we build parks.

Funding

Total Funding: $2,378,000
Funding Sources:
  • Mayoral
  • City Council

Locations

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 12/08/2017