Bronx General Site Work (XG-410M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct play equipment, safety surfacing, pavements, and handball courts at various parks in the Bronx.

Project Timeline

Design

Start Date: November 2009
Completion Date: April 2010

Procurement

Start Date: April 2010
Projected Completion Date: January 2011
Completion Date: October 2011

Construction

Start Date: November 2011
Projected Completion Date: May 2013
Completion Date: September 2013

Understand how we build parks.

Funding

Total Funding: $1,445,000
Funding Sources:
  • Mayoral
  • City Council

Locations

  • Crotona Park, Bronx
    Crotona Park North to South, Fulton Av to Southern Blvd & Crotona Park East
  • Haffen Park, Bronx
    Hammersley Ave. to Burke Ave. bet. Ely Ave. and Gunther Ave.
  • Merriam Playground, Bronx
    W. 168 St. bet. Dr. MLK Jr. Blvd. and Merriam Ave.
  • Morgan Playground, Bronx
    E 168 St bet Park Av & Washington Av
  • Washington's Walk, Bronx
    Resevoir Av bet Sedgwick Av & Goulden Av
 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/16/2017