Bronx River Park Greenway Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct an existing portion and construct a new portion of the Bronx River Greenway.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: July 2010
Projected Completion Date: January 2014
Completion Date: October 2014

Procurement

Start Date: October 2014
Projected Completion Date: July 2015
Completion Date: September 2015

Construction

Start Date: November 2015
Projected Completion Date: February 2017
Completion Date: June 2017

Understand how we build parks.

Funding

Total Funding: $1,968,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council
  • Federal

Location

Bronx Park, Bronx
Unionport Road and Allerton Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 06/23/2017