Yolanda Garcia Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct Yolanda Garcia Park.

Project Timeline

Design

Start Date: April 2008
Projected Completion Date: November 2013
Completion Date: May 2015

Procurement

Start Date: May 2015
Projected Completion Date: February 2016
Completion Date: July 2016

Construction

Start Date: October 2016
Projected Completion Date: September 2019
Completion Date: April 2019

Understand how we build parks.

Funding

Total Funding: $6,627,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Yolanda GarcĂ­a Park , Bronx
Melrose Avenue between East 159th and East 160th Streets

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 09/13/2019