Old Croton Aqueduct Signage Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct signage at several locations along the Old Croton Aqueduct.

Project Timeline

Design

Start Date: June 2010
Projected Completion Date: June 2012
Completion Date: September 2015

Procurement

Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: June 2016

Construction

Start Date: July 2016
Projected Completion Date: July 2017
Completion Date: April 2017

Understand how we build parks.

Funding

Total Funding: $315,000
Funding Source: Mayoral

Locations

  • Aqueduct Walk, Bronx
    Aqueduct Ave. W. bet. W. Fordham Rd. and W. Kingsbridge Rd.
  • Aqueduct Walk, Bronx
    East Burnside Avenue, University Avenue, Morton Place, Harrison Avenue
  • Highbridge Park, Bronx
    Dr. MLK Jr. Blvd. at W. 170 St.
  • Jerome Park, Bronx
    Goulden Av bet W 205 St and Sedgwick Av
  • University Malls, Bronx
    University Av bet W 174 St & W Tremont Av
  • Van Cortlandt Park, Bronx
    NYC - Westchester County Line, Van Cortlandt Park S. bet. Broadway and Jerome Ave.
 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/20/2017