Pelham Parkway Malls Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Pelham Parkway Malls between Boston Road and Wallace Avenue in the Bronx.

Project Timeline

Design

Start Date: February 2013
Projected Completion Date: June 2014
Completion Date: April 2015

Procurement

Start Date: April 2015
Projected Completion Date: January 2016
Completion Date: February 2016

Construction

Start Date: March 2016
Projected Completion Date: March 2018
Completion Date: November 2017

Understand how we build parks.

Funding

Total Funding: $1,594,000
Funding Source: Mayoral

Location

Pelham Parkway , Bronx
Boston Road and Wallace Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 06/22/2021