Aqueduct Walk 182nd Street Comfort Station Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    93% complete

This project will construct a comfort station in Aqueduct Walk.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: August 2006
Projected Completion Date: December 2013
Completion Date: May 2015

Procurement

Start Date: May 2015
Projected Completion Date: February 2016
Completion Date: July 2016

Construction

Start Date: September 2016
Projected Completion Date: March 2018
Adjusted Completion Date: November 2018

Understand how we build parks.

Funding

Total Funding: $1,000,000
Funding Source: Mayoral

Location

Aqueduct Walk , Bronx
Aqueduct Avenue East between West 182nd Street and West 183rd Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/16/2018