Pelham Bay Park Waterfront Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct and restore the shoreline, remove invasive plants, and construct a new pathway to improve public access to the waterfront at Pelham Bay Park.
Project Timeline
Design
Start Date: August 2007
Projected Completion Date:
March 2012
Completion Date:
August 2013
Procurement
Start Date: August 2013
Projected Completion Date:
May 2014
Completion
Date:
March 2014
Construction
Start Date: August 2014
Projected Completion Date:
August 2015
Completion
Date:
September 2015
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Pelham Bay Park
, Bronx
Eastchester Bay between Pelham Bay landfill and Watt Avenue
Project Staff
Project Liaison: Michelle Martell
Contact NYC Parks
about this project
Last updated: 01/22/2021