Crotona Park Nature Center Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct the Nature Center in Crotona Park.

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

Project Timeline

Design

Start Date: September 2013
Projected Completion Date: February 2015
Completion Date: February 2017

Procurement

Start Date: February 2017
Projected Completion Date: November 2017

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • City Council

Location

Crotona Park, Bronx
Crotona Avenue and Crotona Park East in Crotona Park

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/20/2017