Crotona Park Nature Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    48% complete

This project will reconstruct the nature center in Crotona Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: September 2013
Projected Completion Date: February 2015
Completion Date: February 2017

Procurement

Start Date: February 2017
Projected Completion Date: November 2017
Completion Date: November 2017

Construction

Start Date: March 2018
Projected Completion Date: September 2019
Adjusted Completion Date: April 2020

Understand how we build parks.

Funding

Total Funding: $3,491,000
Funding Sources:
  • Mayoral
  • City Council

Location

Crotona Park , Bronx
Crotona Avenue and Crotona Park East

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 03/27/2020