Castle Hill Park Paths Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct paths and landscaping in Castle Hill Park.

Project Timeline

Design

Start Date: November 2011
Projected Completion Date: June 2013
Completion Date: November 2013

Procurement

Start Date: November 2013
Projected Completion Date: August 2014
Completion Date: December 2014

Construction

Start Date: January 2015
Projected Completion Date: January 2016
Completion Date: January 2016

Understand how we build parks.

Funding

Total Funding: $484,000
Funding Source: Borough President

Location

Castle Hill Park , Bronx
Castle Hill Avenue and Hart Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 01/20/2021