Aqueduct Walk Plaza Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the paths, staircase and miscellaneous site work at Aqueduct Walk Plaza in the Bronx.

Project Update: Bids have been opened and are being evaluated.

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: May 2016
Completion Date: March 2017

Procurement

Start Date: March 2017
Projected Completion Date: December 2017
Adjusted Completion Date: April 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Aqueduct Walk, Bronx
Aqueduct Avenue between West 180th Street and West 181st Streets in Aqueduct Walk

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 02/16/2018