Van Cortlandt Park Dog Run Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a dog run in Van Cortlandt Park.

Project Timeline

Design

Start Date: October 2010
Projected Completion Date: May 2013
Completion Date: June 2016

Procurement

Start Date: June 2016
Projected Completion Date: March 2017
Completion Date: June 2017

Construction

Start Date: August 2017
Projected Completion Date: August 2018
Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $334,000
Funding Sources:
  • Mayoral
  • City Council

Location

Van Cortlandt Park , Bronx
Van Cortlandt Park East between Oneida Avenue and East 238th Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 12/15/2018