Agnes Haywood Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    68% complete

This project will reconstruct Agnes Haywood Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: February 2016
Completion Date: April 2016

Procurement

Start Date: April 2016
Projected Completion Date: January 2017
Completion Date: June 2017

Construction

Start Date: July 2017
Projected Completion Date: July 2018
Adjusted Completion Date: December 2018

Understand how we build parks.

Funding

Total Funding: $2,800,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Agnes Haywood Playground , Bronx
Barnes Avenue between East 215th Street and East 216th Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 12/15/2018