Freshkills North Park Pathway and Comfort Station Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    33% complete

This project will construct a new multi-use pathway, overlook structures, and comfort station with composting toilets in the northern section of Freshkills Park.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: October 2012
Projected Completion Date: March 2014
Completion Date: March 2016

Procurement

Start Date: March 2016
Projected Completion Date: December 2016
Completion Date: June 2017

Construction

Start Date: July 2017
Projected Completion Date: January 2020
Adjusted Completion Date: April 2021

Understand how we build parks.

Funding

Total Funding: $30,114,000
Funding Sources:
  • Mayoral
  • State

Location

Freshkills Park , Staten Island
Dean Avenue, West Shore Expressway, Fresh Kills and Main Creek

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 05/29/2020