Freshkills North Park Pathway and Comfort Station Construction
-
100% complete
-
100% complete
-
57% complete
This project will construct a new multi-use pathway, overlook structures, and comfort station with composting toilets in the northern section of Freshkills Park.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: October 2012
Projected Completion Date:
March 2014
Completion Date:
March 2016
Procurement
Start Date: March 2016
Projected Completion Date:
December 2016
Completion
Date:
June 2017
Construction
Start Date: July 2017
Projected Completion Date:
January 2020
Adjusted Completion
Date:
June 2021
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- State
Location
Freshkills Park
, Staten Island
Dean Avenue, West Shore Expressway, Fresh Kills and Main Creek
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 04/19/2021