Freshkills Park North Park Comfort Station and Pathway Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project is for the construction of a comfort station, multi-use pathway, and overlook structures at Freshkills Park North.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2012
Projected Completion Date: March 2014
Completion Date: March 2016

Procurement

Start Date: March 2016
Projected Completion Date: December 2016
Completion Date: June 2017

Construction

Start Date: July 2017
Projected Completion Date: January 2020

Understand how we build parks.

Funding

Total Funding: $22,970,000
Funding Sources:
  • Mayoral
  • State

Location

Freshkills Park, Staten Island
Dean Avenue, West Shore Expressway, Fresh Kills and Main Creek, Staten Island

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 08/04/2017