Freshkills Park North Park Comfort Station and Pathway Construction

  • Design
    100% complete 
  • Procurement
    60% complete 
  • Construction
     

This project is for the construction of a comfort station, multi-use pathway, and overlook structures at Freshkills Park North.

Project Update: Bids have been opened and are being evaluated.

Project Timeline

Design

Start Date: October 2012
Projected Completion Date:March 2014
Completion Date: March 2016

Procurement

Start Date: March 2016
Projected Completion Date:December 2016
Adjusted Completion Date: June 2017

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Grants
  • Mayor
Design of Freshkills Park North Park Comfort Station and Pathway Construction

Location

Freshkills Park, Staten Island
Dean Avenue, West Shore Expressway, Fresh Kills and Main Creek, Staten Island

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 03/26/2017