Freshkills Park North Park Comfort Station and Pathway Construction

  • Design
    100 % complete 
  • Procurement
    60% complete  
  • Construction
     

This project is for the construction of a comfort station, multi-use pathway, and overlook structures at Freshkills Park North.

Project Update: Bids have been opened and are being evaluated.

Project Timeline

Design

Start Date: October 2012
Projected Completion Date: March 2014
Completion Date: March 2016

Procurement

Start Date: March 2016
Projected Completion Date: December 2016
Adjusted Completion Date: June 2017

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Grants
  • Mayor

Location

Freshkills Park , Staten Island
Dean Avenue, West Shore Expressway, Fresh Kills and Main Creek, Staten Island

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 04/28/2017