Lincoln Terrace Park Tennis Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the tennis courts in Lincoln Terrace Park.

Project Timeline

Design

Start Date: September 2010
Projected Completion Date: February 2012
Completion Date: March 2012

Procurement

Start Date: March 2012
Projected Completion Date: December 2012
Completion Date: October 2012

Construction

Start Date: November 2012
Projected Completion Date: November 2013
Completion Date: November 2013

Understand how we build parks.

Funding

Total Funding: $1,365,000
Funding Source: City Council

Location

Lincoln Terrace / Arthur S. Somers Park , Brooklyn
Buffalo Avenue, East New York Avenue, Portal Street, Eastern Parkway

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 06/28/2022

Was this information helpful?