Soundview Park Performance Lawn and Overlook Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new entrance at Rosedale Avenue and a new open lawn area, asphalt paths, benches, park security lighting, and planting in Soundview Park.

Project Timeline

Design

Start Date: January 2007
Projected Completion Date: November 2012
Completion Date: December 2012

Procurement

Start Date: December 2012
Projected Completion Date: September 2013
Completion Date: August 2013

Construction

Start Date: September 2013
Projected Completion Date: March 2015
Completion Date: April 2015

Understand how we build parks.

Funding

Total Funding: $2,725,000
Funding Source: Mayoral

Location

Soundview Park , Bronx
Rosedale Avenue and Lacombe Avenue

 

Project Staff

Project Liaison: Mike Ortiz
Contact NYC Parks about this project

Last updated: 09/30/2022