Citywide Plumbing Systems Reconstruction (CNYG-1007M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the plumbing systems in comfort stations at various park facilities citywide.
Project Timeline
Design
Start Date: December 2006
Completion Date:
March 2007
Procurement
Start Date: March 2007
Projected Completion Date:
November 2007
Completion
Date:
May 2008
Construction
Start Date: June 2008
Projected Completion Date:
June 2011
Completion
Date:
April 2014
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Borough President
- City Council
Locations
-
Alley Pond Park
, Queens
Little Neck Bay to Springfield Boulevard, Union Turnpike -
Bushwick Playground
, Brooklyn
Knickerbocker Avenue between Woodbine Street and Putnam Avenue -
Carver Playground
, Brooklyn
Sumpter Street between Ralph Avenue and Howard Avenue -
Fort Totten Park
, Queens
Fort Totten, Cross Island Parkway, Totten Road to 15 Road -
Hammel Playground
, Queens
Beach 83rd Street & Rockaway Beach Boulevard -
Highbridge Park
, Manhattan
West 189th Street & Amsterdam Avenue -
Inwood Hill Park
, Manhattan
Dyckman Street, Hudson River, Harlem River Ship Canal -
Louis Armstrong Playground
, Queens
37 Avenue between 112 & 113 Streets -
Sixteen Sycamores Playground
, Brooklyn
Schermerhorn & Nevins Street - Middagh Street between Columbia Heights & Furman Street
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 04/19/2021