Citywide Electrical Systems Reconstruction (CNYG-309M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the electrical systems at comfort stations in various parks citywide.

Project Timeline

Design

Start Date: March 2009
Completion Date: March 2009

Procurement

Start Date: March 2009
Projected Completion Date: December 2009
Completion Date: June 2011

Construction

Start Date: July 2011
Projected Completion Date: July 2014
Completion Date: January 2014

Understand how we build parks.

Funding

Total Funding: $490,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/20/2017