Citywide Buildings Reconstruction (CNYG-209M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct buildings and comfort stations in various parks citywide.

Project Timeline

Design

Start Date: August 2009
Completion Date: September 2009

Procurement

Start Date: September 2009
Projected Completion Date: June 2010
Completion Date: July 2010

Construction

Start Date: July 2010
Projected Completion Date: July 2013
Completion Date: February 2015

Understand how we build parks.

Funding

Total Funding: $2,557,000
Funding Sources:
  • Mayoral
  • City Council

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/16/2017