Citywide Electrical Systems Reconstruction (CNYG-907M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct electrical systems in various parks citywide.
Project Timeline
Design
Start Date: December 2006
Completion Date:
March 2007
Procurement
Start Date: March 2007
Projected Completion Date:
November 2007
Completion
Date:
July 2008
Construction
Start Date: August 2008
Projected Completion Date:
August 2011
Completion
Date:
October 2014
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Locations
-
Alley Pond Park
, Queens
Little Neck Bay to Springfield Boulevard, Union Turnpike -
Bushwick Playground
, Brooklyn
Knickerbocker Avenue between Woodbine Street and Putnam Avenue -
Fort Totten Park
, Queens
Fort Totten, Cross Island Parkway, Totten Road to 15 Road -
Hammel Playground
, Queens
Beach 83rd Street & Rockaway Beach Boulevard -
John V. Lindsay East River Park
, Manhattan
Montgomery Street to East 12 Street, FDR Drive -
Sara D. Roosevelt Park
, Manhattan
East Houston Street to Canal Street -
Sixteen Sycamores Playground
, Brooklyn
Schermerhorn & Nevins Street
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 04/23/2021