NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Greenbelt Native Plant Center Heating System Reconstruction (R017-309MA1)

  • Design
    100% complete 
  • Procurement
    100% complete 
  • Construction
    45% complete 

This project will reconstruct the heating system at the Greenbelt Native Plant Center.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: July 2009
Projected Completion Date:July 2012
Completion Date: November 2013

Procurement

Start Date: November 2013
Projected Completion Date:August 2014
Completion Date: March 2015

Construction

Start Date: May 2015
Projected Completion Date:May 2016
Adjusted Completion Date: December 2016

Understand how we build parks.

Funding

Total Funding: $337,000
Funding Source:Mayor

Location

Greenbelt Native Plant Center, Staten Island
Fresh Kills Park

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 01/13/2017

Was this information helpful?