Greenbelt Native Plant Center Heating System Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the heating system at the Greenbelt Native Plant Center.

Project Timeline

Design

Start Date: July 2009
Projected Completion Date: July 2012
Completion Date: November 2013

Procurement

Start Date: November 2013
Projected Completion Date: August 2014
Completion Date: March 2015

Construction

Start Date: May 2015
Projected Completion Date: May 2016
Completion Date: November 2016

Understand how we build parks.

Funding

Total Funding: $91,000
Funding Source: Mayoral

Location

Greenbelt Native Plant Center, Staten Island
Fresh Kills Park

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 09/21/2017