Midland Beach Recreation Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a recreation building at Midland Beach.

Project Timeline

Design

Start Date: October 2007
Projected Completion Date: February 2009
Completion Date: May 2010

Procurement

Start Date: May 2010
Projected Completion Date: February 2011
Completion Date: January 2012

Construction

Start Date: April 2012
Projected Completion Date: October 2013
Completion Date: October 2013

Understand how we build parks.

Funding

Total Funding: $6,009,000
Funding Source: Borough President

Location

Franklin D. Roosevelt Boardwalk and Beach , Staten Island
Father Capodanno Boulevard and Seaview Avenue.

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 10/18/2019