New Springville Greenway Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a 3.2 mile multi-use path running along the edges of Freshkills Park, William T. Davis Wildlife Refuge and La Tourette Park. It will provide pedestrians and bicyclists with both a recreational amenity and a safe travel alternative to the street. Commuters and recreational users traveling along Park Drive North, Travis Avenue and Richmond Avenue, will enjoy the opportunity to overlook and enjoy the parks’ features and natural ecosystems.

Project Timeline

Design

Start Date: August 2009
Projected Completion Date: October 2012
Completion Date: October 2012

Procurement

Start Date: October 2012
Projected Completion Date: July 2013
Completion Date: December 2013

Construction

Start Date: January 2014
Projected Completion Date: July 2015
Completion Date: July 2015

Understand how we build parks.

Funding

Total Funding: $7,800,000
Funding Sources:
  • Mayoral
  • Federal

Locations

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 11/20/2017