Crescent Beach Park Landscape Improvement and Pathway Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    4% complete

This project will construct new paths, seating, and a flag pole and reconstruct the landscape at Crescent Beach Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: June 2011
Projected Completion Date: October 2012
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: October 2017

Construction

Start Date: October 2017
Projected Completion Date: April 2019
Adjusted Completion Date: January 2020

Understand how we build parks.

Funding

Total Funding: $1,798,000
Funding Sources:
  • Mayoral
  • City Council

Location

Crescent Beach Park , Staten Island
Tennyson Drive between Armstrong and Wiman Avenues

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 11/16/2018