Crescent Beach Park Landscape Improvement and Pathway Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct new paths, seating and a tot lot and reconstruct the landscape at Crescent Beach Park.
Project Timeline
Design
Start Date: June 2011
Projected Completion Date:
October 2012
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
September 2016
Completion
Date:
October 2017
Construction
Start Date: October 2017
Projected Completion Date:
April 2019
Completion
Date:
January 2020
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
Crescent Beach Park
, Staten Island
Tennyson Drive between Armstrong and Wiman Avenues
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project