Faber Park Skate Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a plaza-type skate park at Faber Park, including new drainage structures and trees.

Project Timeline

Design

Start Date: July 2011
Projected Completion Date: August 2012
Completion Date: March 2013

Procurement

Start Date: March 2013
Projected Completion Date: November 2013
Completion Date: November 2013

Construction

Start Date: January 2014
Projected Completion Date: January 2015
Completion Date: January 2015

Understand how we build parks.

Funding

Total Funding: $1,695,000
Funding Source: Borough President

Location

Faber Pool and Park , Staten Island
Faber Street and Sharpe Avenue

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 06/22/2021

Was this information helpful?