Highland Park Perimeter Pathways, Fencing and Security Lighting Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the perimeter pathways, fencing, and security lighting around Ridgewood Reservoir in Highland Park

Project Timeline

Design

Start Date: October 2008
Projected Completion Date: June 2009
Completion Date: January 2010

Procurement

Start Date: January 2010
Projected Completion Date: October 2010
Completion Date: March 2011

Construction

Start Date: May 2011
Projected Completion Date: February 2012
Completion Date: September 2013

Understand how we build parks.

Funding

Total Funding: $6,744,000
Funding Source: Mayoral

Location

Highland Park , Queens
Highland Boulevard, Vermont Place, Jackie Robinson Parkway.

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/27/2020