Queens General Site Work (QG-112M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will reconstruct play equipment, safety surfacing, handball courts, basketball courts, pavement, fencing, plantings and general site work in Queens.

Project Timeline


Start Date: July 2011
Completion Date: August 2011


Start Date: August 2011
Projected Completion Date: May 2012
Completion Date: August 2012


Start Date: January 2013
Projected Completion Date: January 2015
Completion Date: October 2014

Understand how we build parks.


Total Funding: $3,031,000
Funding Sources:
  • Mayoral
  • State



Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 03/23/2018