Flushing Meadows Corona Park Pavement and Fence Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct pavements and fences at the tennis courts and near the LIRR tracks in Flushing Meadows Corona Park.
Project Timeline
Design
Start Date: November 2010
Completion Date:
June 2011
Procurement
Start Date: June 2011
Projected Completion Date:
March 2012
Completion
Date:
September 2012
Construction
Start Date: October 2012
Projected Completion Date:
April 2014
Completion
Date:
September 2013
Understand how we build parks.
Funding
Funding Source: Federal
Location
Flushing Meadows Corona Park
, Queens
Grand Central Pkwy., Whitestone Exwy. bet. 111 St. and College Point Blvd., Park Drive E.
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project
Last updated: 07/05/2022