Flushing Meadows Corona Park Pavement and Fence Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct pavements and fences at the tennis courts and near the LIRR tracks in Flushing Meadows Corona Park.

Project Timeline

Design

Start Date: November 2010
Completion Date: June 2011

Procurement

Start Date: June 2011
Projected Completion Date: March 2012
Completion Date: September 2012

Construction

Start Date: October 2012
Projected Completion Date: April 2014
Completion Date: September 2013

Understand how we build parks.

Funding

Total Funding: $289,000
Funding Sources:
  • Mayoral
  • Federal

Location

Flushing Meadows Corona Park, Queens
Grand Central Pkwy., Whitestone Exwy. bet. 111 St. and College Point Blvd., Park Drive E.

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/20/2017