Queens General Site Work (QG-811M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct play equipment, safety surfacing, pavements, fencing, tennis courts, handball courts and plantings at various parks in Queens.

Project Timeline

Design

Start Date: February 2011
Completion Date: April 2011

Procurement

Start Date: April 2011
Projected Completion Date: December 2011
Completion Date: January 2012

Construction

Start Date: March 2012
Projected Completion Date: September 2013
Completion Date: September 2013

Understand how we build parks.

Funding

Total Funding: $1,521,000
Funding Sources:
  • Borough President
  • City Council

Locations

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 01/23/2020