Rockaway Beach Skate Park Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct a skate park facility located between Beach 91st and Beach 92nd Streets at Rockaway Beach.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: April 2016
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President

Location

Rockaway Beach Boardwalk , Queens
South of Shore Front Parkway at Rockaway Beach between Beach 91st Street and Beach 92nd Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/20/2018