Rockaway Beach Skate Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    91% complete

This project will reconstruct the skate park at Rockaway Beach.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: April 2016
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: July 2019

Construction

Start Date: September 2019
Projected Completion Date: December 2020

Understand how we build parks.

Funding

Total Funding: $3,536,000
Funding Sources:
  • Mayoral
  • Borough President
  • Federal

Location

Rockaway Beach Boardwalk , Queens
Shore Front Parkway between Beach 91st Street and Beach 92nd Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/11/2020