Idlewild Park Nature Center Construction
-
100% complete
-
100% complete
-
22% complete
This project will construct a nature center in Idlewild Park.
Project Update: This project is in active construction.
Project Timeline
Design
Start Date: May 2010
Projected Completion Date:
June 2013
Completion Date:
October 2016
Procurement
Start Date: October 2016
Projected Completion Date:
July 2017
Completion
Date:
May 2018
Construction
Start Date: September 2018
Projected Completion Date:
February 2020
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Borough President
Location
Idlewild Park
, Queens
149th Avenue and Springfield Lane
Project Staff
Project Liaison: Joanne Amagrande
Contact NYC Parks
about this project
Last updated: 12/12/2019