Idlewild Park Nature Center Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    69% complete

This project will construct a nature center in Idlewild Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: May 2010
Projected Completion Date: June 2013
Completion Date: October 2016

Procurement

Start Date: October 2016
Projected Completion Date: July 2017
Completion Date: May 2018

Construction

Start Date: September 2018
Projected Completion Date: February 2020
Adjusted Completion Date: December 2020

Understand how we build parks.

Funding

Total Funding: $8,173,000
Funding Sources:
  • Mayoral
  • Borough President

Location

Idlewild Park , Queens
149th Avenue and Springfield Lane

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 10/22/2020