Rufus King Park Gazebo Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the gazebo and construct new pathways in Rufus King Park.

Project Timeline

Design

Start Date: October 2011
Projected Completion Date: June 2013
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: August 2014
Completion Date: January 2015

Construction

Start Date: March 2015
Projected Completion Date: March 2016
Completion Date: November 2016

Understand how we build parks.

Funding

Total Funding: $1,718,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Rufus King Park , Queens
150th Street, 153rd Street, Jamaica Avenue, 84th Avenue

 