Alley Pond Park Paths and Drainage Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the paths and address drainage issues at Oakland Lake in Alley Pond Park.

Project Timeline

Design

Start Date: March 2011
Projected Completion Date: October 2013
Completion Date: November 2013

Procurement

Start Date: November 2013
Projected Completion Date: August 2014
Completion Date: July 2014

Construction

Start Date: September 2014
Projected Completion Date: September 2015
Completion Date: August 2015

Understand how we build parks.

Funding

Total Funding: $1,288,000
Funding Sources:
  • Borough President
  • City Council

Location

Alley Pond Park , Queens
46th Avenue between Springfield and Cloverdale Boulevards, Alley Pond Park

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 04/25/2019