Alley Pond Environmental Center Reconstruction
-
100% complete
-
100% complete
-
34% complete
This project will construct a new environmental center in Alley Pond Park.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: February 2010
Projected Completion Date:
July 2013
Completion Date:
August 2017
Procurement
Start Date: August 2017
Projected Completion Date:
May 2018
Completion
Date:
July 2019
Construction
Start Date: September 2019
Projected Completion Date:
September 2021
Adjusted Completion
Date:
December 2021
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Borough President
- City Council
Location
Alley Pond Park
, Queens
Northern Boulevard and Cross Island Parkway
Project Staff
Project Liaison: Joanne Amagrande
Contact NYC Parks
about this project
Last updated: 01/15/2021