Alley Pond Environmental Center Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will construct a new environmental center in Alley Pond Park.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: February 2010
Projected Completion Date: July 2013
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: May 2018
Adjusted Completion Date: June 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Alley Pond Park , Queens
Northern Boulevard and Cross Island Parkway, Queens

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 01/15/2019