Alley Pond Environmental Center Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will construct a new environmental center in Alley Pond Park.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: February 2010
Projected Completion Date: July 2013
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: May 2018
Adjusted Completion Date: December 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Alley Pond Park , Queens
Northern Boulevard and Cross Island Parkway, Queens

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 10/18/2018