Olde Towne of Flushing Burial Ground Monument Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a monument at The Olde Towne of Flushing Burial Ground.

Project Timeline

Design

Start Date: April 2018
Projected Completion Date: April 2019
Completion Date: March 2019

Procurement

Start Date: March 2019
Projected Completion Date: December 2019
Completion Date: March 2020

Construction

Start Date: September 2020
Projected Completion Date: August 2021
Completion Date: August 2021

Understand how we build parks.

Funding

Total Funding: $1,466,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

The Olde Towne of Flushing Burial Ground , Queens
46th Avenue between 164th Street and 165th Street

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 08/05/2022

Was this information helpful?