Bowne Park Bocce Court Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a bocce court in Bowne Park.

Project Timeline

Design

Start Date: July 2011
Projected Completion Date: January 2012
Completion Date: February 2012

Procurement

Start Date: February 2012
Projected Completion Date: October 2012
Completion Date: September 2012

Construction

Start Date: October 2012
Projected Completion Date: October 2013
Completion Date: August 2013

Understand how we build parks.

Funding

Total Funding: $267,000
Funding Sources:
  • City Council
  • State

Location

Bowne Park , Queens
29th Avenue and 158th Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/28/2020