Bowne House Restoration

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will restore the exterior and address interior structural issues of the Bowne House in Margaret I. Carmen Green – Weeping Beech.

Project Timeline

Design

Start Date: May 2010
Completion Date: October 2011

Procurement

Start Date: October 2011
Projected Completion Date: July 2012
Completion Date: November 2012

Construction

Start Date: April 2013
Projected Completion Date: May 2014
Completion Date: November 2014

Understand how we build parks.

Funding

Total Funding: $2,748,000
Funding Sources:
  • Borough President
  • State

Location

Margaret I. Carman Green - Weeping Beech , Queens
Bowne Street between 37th and 38th Avenues, Weeping Beech Park, Queens

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 07/31/2020