Frank Principe Park Ballfields Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    69% complete

This project will construct a synthetic turf soccer field and reconstruct two ballfields with synthetic turf in Frank Principe Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2015
Projected Completion Date: May 2016
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017
Completion Date: October 2017

Construction

Start Date: November 2017
Projected Completion Date: January 2019

Understand how we build parks.

Funding

Total Funding: $4,649,000
Funding Source: City Council

Location

Frank Principe Park , Queens
63rd Street, 54th Avenue, Maurice Avenue, and Borden Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/15/2018