Juniper Valley Park Bocce Court Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct and expand the bocce court area in Juniper Valley Park with an additional bocce court, shade canopies, a sitting area, benches, and trees.

Project Timeline

Design

Start Date: July 2011
Projected Completion Date: January 2012
Completion Date: November 2012

Procurement

Start Date: November 2012
Projected Completion Date: August 2013
Completion Date: June 2013

Construction

Start Date: September 2013
Projected Completion Date: September 2014
Completion Date: September 2014

Understand how we build parks.

Funding

Total Funding: $741,000
Funding Sources:
  • Borough President
  • City Council

Location

Juniper Valley Park , Queens
Juniper Boulevard North between 78th Street and 80th Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 01/27/2020