Athens Square Playground Plaza Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the plaza and adjacent seating area in Athens Square Playground. The cheek walls on either side of the two ramps will be reconstructed and a new ramp will be constructed between the seating area and the plaza. New handrails will be installed, 2 1/2 foot fencing will be placed around plant beds, plant material will be replaced as needed, and a trench drain will be installed near the spray shower to keep water from flowing onto the safety surface.

Project Timeline

Design

Start Date: March 2011
Completion Date: January 2012

Procurement

Start Date: January 2012
Projected Completion Date: October 2012
Completion Date: November 2012

Construction

Start Date: July 2013
Projected Completion Date: July 2014
Completion Date: August 2014

Understand how we build parks.

Funding

Total Funding: $620,000
Funding Source: Borough President

Location

Athens Square , Queens
30th Street and 30th Avenue, Queens

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project