Flushing Meadows Corona Park Meadow Lake Habitat Restoration

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will restore the habitat and construct stormwater treatment and sitework elements at Meadow Lake in Flushing Meadows-Corona Park.

Project Timeline

Design

Start Date: April 2011
Projected Completion Date: January 2014
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: September 2014
Completion Date: November 2014

Construction

Start Date: January 2015
Projected Completion Date: January 2016
Completion Date: May 2016

Understand how we build parks.

Funding

Total Funding: $2,133,000
Funding Sources:
  • Mayoral
  • City Council
  • State

Location

Flushing Meadows Corona Park, Queens
Grand Central Parkway, Flushing Meadows-Corona Park, Queens

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/20/2017