Manhattan Roofing Reconstruction (MG-709M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct roofs at various facilities in Manhattan.

Project Timeline

Design

Start Date: September 2008
Completion Date: March 2009

Procurement

Start Date: March 2009
Projected Completion Date: December 2009
Completion Date: December 2009

Construction

Start Date: January 2010
Projected Completion Date: January 2013
Completion Date: August 2015

Understand how we build parks.

Funding

Total Funding: $2,675,000
Funding Sources:
  • Mayoral
  • City Council

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/20/2017