Fort Washington Park Ballfields Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the ballfields in Fort Washington Park.

Project Timeline

Design

Start Date: September 2010
Projected Completion Date: August 2011
Completion Date: January 2012

Procurement

Start Date: January 2012
Projected Completion Date: October 2012
Completion Date: August 2012

Construction

Start Date: September 2012
Projected Completion Date: September 2013
Completion Date: October 2013

Understand how we build parks.

Funding

Total Funding: $2,577,000
Funding Source: Mayoral

Location

Fort Washington Park, Manhattan
Between West 164th Street and West 167th Street.

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/20/2017