Fort Washington Park Greenway Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new waterfront mixed-use path in Fort Washington Park.

Project Timeline

Design

Start Date: August 2009
Projected Completion Date: January 2011
Completion Date: January 2011

Procurement

Start Date: January 2011
Projected Completion Date: October 2011
Completion Date: April 2012

Construction

Start Date: June 2012
Projected Completion Date: June 2013
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $3,192,000
Funding Sources:
  • Mayoral
  • Federal

Location

Fort Washington Park, Manhattan
Between Dyckman Street and West 188th Street

 

Project Staff

Project Liaison: Steve Simon