Fort Washington Park Dyckman Street Ramp Construction and Inwood Hill Park Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct an accessible ramp from the Hudson River Greenway to Dyckman Street in Fort Washington Park. It will also reconstruct the entrance to Inwood Hill Park at Dyckman Street near the Hudson River and create a multi-use path between that entrance and the pedestrian bridge over the Amtrak rail line.

Project Timeline


Start Date: January 2009
Projected Completion Date: October 2009
Completion Date: January 2012


Start Date: January 2012
Projected Completion Date: September 2012
Completion Date: October 2012


Start Date: December 2012
Projected Completion Date: September 2014
Completion Date: June 2015

Understand how we build parks.


Total Funding: $6,358,000
Funding Sources:
  • Mayoral
  • Federal



Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 03/16/2018