Battery Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct and expand the playground at The Battery.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: October 2015
Projected Completion Date: October 2017
Completion Date: March 2019

Procurement

Start Date: March 2019
Projected Completion Date: December 2019
Completion Date: November 2019

Construction

Start Date: December 2019
Projected Completion Date: March 2021

Understand how we build parks.

Funding

Total Funding: $18,300,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council
  • Federal
  • Private

Location

The Battery , Manhattan
State Street and Peter Minuit Plaza

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 12/06/2019