Battery Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    44% complete

This project will reconstruct and expand the playground at The Battery.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: October 2015
Projected Completion Date: October 2017
Completion Date: March 2019

Procurement

Start Date: March 2019
Projected Completion Date: December 2019
Completion Date: November 2019

Construction

Start Date: December 2019
Projected Completion Date: March 2021
Adjusted Completion Date: May 2021

Understand how we build parks.

Funding

Total Funding: $21,300,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council
  • Federal
  • Private

Location

The Battery , Manhattan
State Street and Peter Minuit Plaza

 