Highbridge Park Brush Stairway Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will demolish and reconstruct the Brush Stairway in Highbridge Park

Project Timeline

Design

Start Date: May 2009
Projected Completion Date: January 2010
Completion Date: November 2010

Procurement

Start Date: November 2010
Projected Completion Date: August 2011
Completion Date: July 2011

Construction

Start Date: September 2011
Projected Completion Date: September 2012
Completion Date: February 2014

Understand how we build parks.

Funding

Total Funding: $765,000
Funding Sources:
  • Borough President
  • Private

Location

Highbridge Park, Manhattan
Near West 158th Street between Edgecombe Avenue and Harlem River Drive

 