Fort Tryon Park Fieldhouse Staircase Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the staircase and perform site work at the Fort Tryon Park fieldhouse.

Project Timeline


Start Date: February 2011
Projected Completion Date: January 2015
Completion Date: December 2015


Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: December 2016


Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: March 2018

Understand how we build parks.


Total Funding: $1,094,000
Funding Source: Borough President


Fort Tryon Park , Manhattan
Broadway between Arden Street and Dongan Place, Manhattan


Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 03/21/2018