Sherman Creek Entrance, Path, and Fencing Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct an entrance, path and fencing at Sherman Creek.

Project Timeline

Design

Start Date: April 2006
Projected Completion Date: September 2012
Completion Date: October 2012

Procurement

Start Date: October 2012
Projected Completion Date: July 2013
Completion Date: June 2013

Construction

Start Date: September 2013
Projected Completion Date: September 2014
Completion Date: May 2014

Understand how we build parks.

Funding

Total Funding: $433,000
Funding Source: City Council

Location

Sherman Creek , Manhattan
Dyckman Street at 10th Avenue

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/18/2019