Randall's Island Western Shore Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct a portion of the western shore on Randall's Island.

Project Update: The Agency was required to secure additional funding to award the project.

Project Timeline

Design

Start Date: September 2011
Projected Completion Date: June 2016
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: May 2017
Adjusted Completion Date: September 2017

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • State

Location

Randall's Island Park, Manhattan
Randall's Island, Harlem River

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 06/23/2017